Quote
2025-A-01-32
Issued
Issued
29 January , 2025
29 January , 2025
From
From
Crystal Precision
09942469020
9581 Provincial Road, Purok Maganda, Barangay Gulang Gulang, Lucena City, 4301 Quezon, Philippines
Crystal Precision
09942469020
9581 Provincial Road, Purok Maganda, Barangay Gulang Gulang, Lucena City, 4301 Quezon, Philippines
To
To
Japhoi Villanueva
Bucal, Calamba, Laguna
Japhoi Villanueva
Bucal, Calamba, Laguna
About the project
About the project
Project Description: Cabinetry Project for Mr. Japhoi Villanueva at Calamba City, Laguna
This project details the design, fabrication, and installation of custom cabinets for Mr. Japhoi Villanueva's Project in Calamba City, Laguna. Our focus is on creating highly functional, durable, and aesthetically pleasing cabinetry specifically engineered to withstand the local climate.
Project Description: Cabinetry Project for Mr. Japhoi Villanueva at Calamba City, Laguna
This project details the design, fabrication, and installation of custom cabinets for Mr. Japhoi Villanueva's Project in Calamba City, Laguna. Our focus is on creating highly functional, durable, and aesthetically pleasing cabinetry specifically engineered to withstand the local climate.
Deliverables
Deliverables
Ground Floor Main Kitchen


Unit Price`
₱ 281,000
Qty.
1 package
₱ 281,000
Ground Floor Dirty Kitchen


Unit Price`
₱ 181,000
Qty.
1 package
₱ 181,000
Second Floor Walk-in Closet


Unit Price`
₱ 243,000
Qty.
1 package
₱ 243,000
Total
₱ 705,000
Project Summary
Project Summary
Total Contract Price: ₱ 705,000
I. Materials & Key Features
Stated above
II. Project Timeline (Estimated 4–8 Weeks)
Procurement (Weeks 1–2): Material sourcing and final site validation.
Fabrication (Weeks 3–6): Off-site precision cutting and assembly.
Installation (7–10 Days): On-site mounting, quartz fitting, and electrical integration.
III. Payment Schedule
50% Initial Commitment (₱ 356,000): Due upon signing to secure materials and production slot.
30% Installation Progress (₱ 213,600): Due upon arrival of materials and 50% on-site completion.
20% Final Turnover (₱ 142,400): Due upon 100% completion, plumbing/electrical testing, and final walkthrough.
IV. Warranty & Terms
Service Warranty: 6-Month Workmanship Warranty covering structural adjustments and installation quality from the date of turnover.
Validity: This proposal remains valid for 15 days.
Total Contract Price: ₱ 705,000
I. Materials & Key Features
Stated above
II. Project Timeline (Estimated 4–8 Weeks)
Procurement (Weeks 1–2): Material sourcing and final site validation.
Fabrication (Weeks 3–6): Off-site precision cutting and assembly.
Installation (7–10 Days): On-site mounting, quartz fitting, and electrical integration.
III. Payment Schedule
50% Initial Commitment (₱ 356,000): Due upon signing to secure materials and production slot.
30% Installation Progress (₱ 213,600): Due upon arrival of materials and 50% on-site completion.
20% Final Turnover (₱ 142,400): Due upon 100% completion, plumbing/electrical testing, and final walkthrough.
IV. Warranty & Terms
Service Warranty: 6-Month Workmanship Warranty covering structural adjustments and installation quality from the date of turnover.
Validity: This proposal remains valid for 15 days.